Hi Community,

I just can’t get the upload feature work properly in the Weekly Crew Time Entry.

When it reads the upload file all fields are ok except date and time, I did numerous tests changing the format of these fields but still Acumatica can’t process it and so I have to manually enter them which is time wasting.

Are any of you successfully using this feature? Can you share a working upload file so I can test and try to figure out where my setup is wrong?

 

Thanks in advanced,

Abel

Best answer by DavidEichner

I was able to import the file you sent after updating the employee and removing the Project references. It might be a bug in the version/build you are on.  I would start a support case with Acumatica to verify and perhaps see if they have fixed it in a more recent build of 2021R1 or if you would need to update to more recent version/build. 

Also, you might try not importing Project data to see if the issue is with Project Accounting.

Best,

David Eichner, CPA

View original
Did this topic help you find an answer to your question?

10 replies

DavidEichner
Captain II
Forum|alt.badge.img+13
  • Captain II
  • 373 replies
  • January 19, 2023

Hi Abel,

What version of Acumatica are you running on? I was able to import the attached file into the sales demo company.  Often times, it helps to manually enter a record first and then export to Excel so you can see the way the Excel columns should be configured.

Best,

David Eichner, CPA


  • Author
  • Freshman I
  • 6 replies
  • January 19, 2023

Hi David,

Thanks, sorry I should have included more detail here:

Acumatica release 2021 R1

Error message attached

I did the exercise export to excel and then upload, same problem. Also tried with your example and that didn’t work either. I am suspecting some other kind of setup issue, hope the error message gives a glimpse here.


  • Author
  • Freshman I
  • 6 replies
  • January 19, 2023

..and this is how it looks after pressing OK to the error message


DavidEichner
Captain II
Forum|alt.badge.img+13
  • Captain II
  • 373 replies
  • January 19, 2023

I am on 2022R2 latest build.  If you’d like me to try importing with your file, you can either email it to me at deichner@kensium.com or attach the Excel file to this thread.

Best,

David Eichner, CPA


  • Author
  • Freshman I
  • 6 replies
  • January 19, 2023

File attached here.

 

Thanks David.


DavidEichner
Captain II
Forum|alt.badge.img+13
  • Captain II
  • 373 replies
  • Answer
  • January 19, 2023

I was able to import the file you sent after updating the employee and removing the Project references. It might be a bug in the version/build you are on.  I would start a support case with Acumatica to verify and perhaps see if they have fixed it in a more recent build of 2021R1 or if you would need to update to more recent version/build. 

Also, you might try not importing Project data to see if the issue is with Project Accounting.

Best,

David Eichner, CPA


DavidEichner
Captain II
Forum|alt.badge.img+13
  • Captain II
  • 373 replies
  • January 19, 2023

Here’s a copy of the test file I used without Project data


  • Author
  • Freshman I
  • 6 replies
  • January 19, 2023

That makes sense, even the error message seemed to be claiming about other things than date&time.

Very much appreciated David, thanks for your kind support.

Have a joyful 2023.


  • Author
  • Freshman I
  • 6 replies
  • February 13, 2023

Hi,

 

For those interested on the topic this error was solved after upgrade to 2022R2.

 

Cheers,

Abel


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • 2640 replies
  • February 13, 2023

Thank you for providing this update to the community @abelp !


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings