Hi, We are currently piloting the Acumatica production order system. We are planning on using Advanced Planning to schedule production orders.
When we run scheduling from rough cut planning screen , most of the production orders schedule just fine. We however, have a few that will not schedule. I suspect that this is due to some material constraints. These are lower level production orders generated from the ‘generate sub assemply’ feature on production orders.
For the production order type, we are not checking for material availability
For each of the detail items on the production order on the material tab - we have set to do not check material availability.
Our issue, is that the system gives us no clue or message as to why the production order will not schedule. There are no error messages or warnings, so it is very difficult to figure out why it will not schedule.
Does anyone have any tips on how I might figure out why a production order will not schedule given the limitations on feedback related to constraints?
Thanks,
Bob