The action dates for the purchase items shown in the inventory planning display do not match, even though all the purchase items within the box are used to manufacture the same item for the same sales order. Additionally, no lead time is specified for these purchase items, and there is no available quantity in the warehouse.
Best answer by karthikvt78
I would recommend you reach out to Acumatica support. This may be a known issue.
Possibly AC-343636 - Issue Description:
On the Inventory Planning Display (AM400000) form, when a record with the Manufacturing source was generated, the system incorrectly assigned it the action date from the previously processed record with the same source. This resulted in incorrect inventory planning recommendations, potentially causing users to have production orders created either later or earlier than required.
System calculates lead time for each operation in the BOM of a finished good and adjusts the purchase action time of component items based on the operation start time to minimize inventory carrying costs. This could be the reason for the difference in action dates.
I would recommend you reach out to Acumatica support. This may be a known issue.
Possibly AC-343636 - Issue Description:
On the Inventory Planning Display (AM400000) form, when a record with the Manufacturing source was generated, the system incorrectly assigned it the action date from the previously processed record with the same source. This resulted in incorrect inventory planning recommendations, potentially causing users to have production orders created either later or earlier than required.
I would recommend you reach out to Acumatica support. This may be a known issue.
Possibly AC-343636 - Issue Description:
On the Inventory Planning Display (AM400000) form, when a record with the Manufacturing source was generated, the system incorrectly assigned it the action date from the previously processed record with the same source. This resulted in incorrect inventory planning recommendations, potentially causing users to have production orders created either later or earlier than required.
System calculates lead time for each operation in the BOM of a finished good and adjusts the purchase action time of component items based on the operation start time to minimize inventory carrying costs. This could be the reason for the difference in action dates.