Skip to main content
Answer

Honor vendor (business account) calendar in MRP Regeneration

  • November 6, 2020
  • 1 reply
  • 103 views

Forum|alt.badge.img

Asian suppliers observe holiday periods where their factories are shut down.  Other suppliers may have periods where their factories are closed for holiday, plant shutdown, etc.  You can associate a calendar to the underlying vendor’s business account.  If a calendar exists then use this calendar to move the  planned order promise date and action dates to working days.

 

This could be extended to manual created purchase orders also.

Best answer by vkumar

Hi @dennisgodsill36 

You may post this feature request on our Product idea page as well (https://community.acumatica.com/ideas).

Regards,

1 reply

Forum|alt.badge.img+12
  • Acumatica Support Team
  • Answer
  • November 6, 2020

Hi @dennisgodsill36 

You may post this feature request on our Product idea page as well (https://community.acumatica.com/ideas).

Regards,