Cost Roll Calculation Error - Manufactured Items from Other Branches

  • March 17, 2026
  • 2 replies
  • 24 views

When performing a mass multi‑level cost roll, Acumatica doesn't recalculate bill levels for manufactured items from other branches or update their costs in the receiving branch’s assembly. It simply uses the existing standard cost.

As a workaround, the mass cost roll process must be run twice. The first run does not pull the most recent standard cost from the sending branch, resulting in an inaccurate assembly cost in the receiving branch. The second run then captures the correct sending‑branch cost and updates the assembly cost appropriately.

Can the cost roll process be corrected instead of repeating the mass cost roll process?

2 replies

dgodsill97
Varsity I
Forum|alt.badge.img+6
  • Varsity I
  • March 18, 2026

Is the bill of material for the upper level, we will call it branch A, have the lower level, branch B, as a component with a branch B warehouse?  Then it should work.  It is set up as branch A warehouse with a replenishment method of transfer from branch B then it does not work - been like that for years - because the cost roll only looks for components with replenishment source of manufacturing in Branch A.


Forum|alt.badge.img+3

@mhensleytn May I know version of Acumatica you are trying this, I know in 25R2 acumatica changed cost roll process