When performing a mass multi‑level cost roll, Acumatica doesn't recalculate bill levels for manufactured items from other branches or update their costs in the receiving branch’s assembly. It simply uses the existing standard cost.
As a workaround, the mass cost roll process must be run twice. The first run does not pull the most recent standard cost from the sending branch, resulting in an inaccurate assembly cost in the receiving branch. The second run then captures the correct sending‑branch cost and updates the assembly cost appropriately.
Can the cost roll process be corrected instead of repeating the mass cost roll process?