Automation Schedule on Generate from Service Contracts

  • November 15, 2022
  • 5 replies
  • 138 views

kristianharianja
Semi-Pro I
Forum|alt.badge.img+3

I can’t get this to work despite executed, I am wondering what’s missing.

These are schedules ready to process:
 

 

Automation schedule:

 

 

 

5 replies

Manikanta Dhulipudi
Captain II
Forum|alt.badge.img+15

Hi @kristianharianja  

Are you able to process t manually?

If your schedules aren’t running, make sure they are active first and if the “Initialize Scheduler” button is enabled on the “Automation Schedules” screen, make sure to check it to start/restart the scheduler itself.

Also can you provide start ,End time and every once and check 

Thanks


Anacarina Calvo
Pro I
Forum|alt.badge.img+4

Hi @kristianharianja 
Also, if this will be a schedule that runs daily, do not add a fixed date on the Generate Up To filter because once the schedules are generated up to that date, there will not be any pending schedules to process 


kristianharianja
Semi-Pro I
Forum|alt.badge.img+3

Hi @manikantad18

This is the status of the schedule, looks fine. The schedule is actually running and executed.

 

 

And did as you suggested:

 

But that doesn't successfully generate any new order.


kristianharianja
Semi-Pro I
Forum|alt.badge.img+3

​​Hi @Anacarina Calvo  

The idea is to generate service order 2 weeks in advance for planning, allocating manpower, stock, etc and we want this to be automatically generated without manual generation. 

I set the Generate Up To date as relative so that system always looks at 2 weeks ahead.


kristianharianja
Semi-Pro I
Forum|alt.badge.img+3

Hi @manikantad18 

Also I am able to run the process manually.