Projects - change in rate

  • 27 October 2023
  • 2 replies
  • 34 views

Userlevel 2

We use the projects module and our rates change periodically.  I know my changes for 2024 now but still need to bill under old rates until January.  Is there a way I can enter the rates now and have them become effective on a specific date in the future?

icon

Best answer by Laura02 27 October 2023, 19:54

View original

2 replies

Badge +18

Hello,

Are you asking about Labor Rates?  Labor Rates do have Effective Dates that will automatically take effect on 1/1/2024”

Are you asking about Billing Rates?  Rate Tables also have Effective Dates:

If you are only using a Billing Rule (no Rate Tables), then you will need to replace the rate in the billing rule on 1/1/2024.

New Costs can be entered to Inventory Items early and left  Pending. Update costs on 1/1/2024 manually or via a schedule.

Laura

Userlevel 2

Got it!!  Thank you so much - we are using billing rules.

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.