Hi, we are in the situation where we often have 1 quoted amount for multiple items. We are not provided per item pricing and some items are not in our inventory.
Items are typically shipped over time, so we are receiving incrementally.
We have need to track the quantities with descriptions, so we’ve set up non-stock “quoted lot” for items not currently in inventory, and use stock part numbers if existing. These are on the PO at zero cost.
We have found that when received, the line items with $0 cost are not flowing into the project cost code transactions. How do we pass this info to the project without requiring a cost to be received on the PO?