How to Track Subcontractor Submitted/Invoiced Quantities

  • November 13, 2025
  • 5 replies
  • 57 views

Hi all - 

We are in the heavy civil construction industry; when paying for subcontractors, we can only pay what paid (meaning, if the open commitment quantity is for 10 units, and we are only paid 7 units from the project owner, we can only pay the subcontractor 7 units). 

We receive invoices from the subcontractors for work complete, but there’s no way to track that quantity in any report. We currently use Progress Worksheets in the Construction module to log the invoices, but these “completed quantities” don’t go anywhere/aren’t reportable/can’t tie to project commitments. 

How are others tracking the submitted/invoiced quantities for subcontracts, but not actually entering the invoices into payables? 

 

Best answer by nickcerri32

@amillerbernd If you’re already using Progress Worksheets you can write a fairly simple GI to pull data from the PMProgressWorksheetLine and PMProgressWorksheet DACs.  I’ve attached one that is super simple, but you can modify it to your liking and add pivot tables after you publish it.  Note that it is for 25R1.

5 replies

nickcerri32
Varsity I
Forum|alt.badge.img+2
  • Varsity I
  • Answer
  • November 14, 2025

@amillerbernd If you’re already using Progress Worksheets you can write a fairly simple GI to pull data from the PMProgressWorksheetLine and PMProgressWorksheet DACs.  I’ve attached one that is super simple, but you can modify it to your liking and add pivot tables after you publish it.  Note that it is for 25R1.


  • Author
  • Freshman I
  • December 12, 2025

Hey Nick; thanks for your feedback & resources. We’re trying to link these units to specific subcontracts (example - we have (3) subcontracts that are submitting invoices/quantities to the same cost budget task). While this is definitely a useful tool, it doesn’t really fulfil the need we’re looking for. I’m trying to find a way to enter a Subcontract/Project Commitment Receipt to track these quantities. Thanks! 


nickcerri32
Varsity I
Forum|alt.badge.img+2
  • Varsity I
  • December 12, 2025

@amillerbernd - Just so I’m clear, are you trying to mimic the PO workflow (Purchase Order > Purchase Receipt) for Subcontracts?  Subcontracts effectively skip the receipt step in that workflow and go straight to billing.


  • Author
  • Freshman I
  • December 12, 2025

Hi Nick,

You’re right, subcontracts in Acumatica do skip the receipt step, that’s what I’m trying to work through as we need to capture the receipt to submit & reconcile billing. 

I am trying to mimic the PO workflow, not the PO billing rules. 

When subcontractors submit quantities/invoices to us, it’s not 100% guaranteed they will be paid those exact numbers - their price stays the same, but units paid fluctuates. We work in a “Pay When Paid, Pay What Paid” industry - meaning, we don’t pay subcontractors when we receive a bill, we pay them within a certain timeframe (typically 2-ish weeks) after receiving payment from the project owner. 

At that time, the subcontractor may have invoiced for 100 units, but if we only receive payment from the project owner for 95 units, we can only pay the subcontractor 95 units. Does that help/make sense?  


nickcerri32
Varsity I
Forum|alt.badge.img+2
  • Varsity I
  • December 12, 2025

@amillerbernd - Just a quick clarification:  When you say you’re trying to mimic the workflow but not the billing rules.  What specifically do you mean by this?

Have you considered doing away with Subcontracts altogether and using the PO workflow instead, leveraging a non-stock item, cost code, etc. to distinguish Subcontracts?  This would allow you to use PO Receipts.