Cost equipment to project at weekly or daily or monthly rates

  • 3 August 2023
  • 2 replies
  • 68 views

Userlevel 1

What solutions have you implemented for costing equipment to projects at non-hourly rates? For example e a company owned jobsite trailer is on the project and they’d like that to cost to the project at a monthly rate for so long as it is onsite. Other equipment gets costed weekly or on daily basis. They’d like to assign the equipment and have it allocate automatically, not relying on equipment timecard entries.  I have a couple ideas but interested in hearing what has worked for others. 

icon

Best answer by chidao 4 August 2023, 04:30

View original

2 replies

We have the same discussion w our partner as they said it’s not default from system. This should be customized to link FA w Project so we can run depreciate that equipment to project.

Userlevel 4
Badge

Assignar does this well. 

 

I don’t use Equpment time cards with any of my clients. The system also lacks any functionality for entering equipment repairs through AP or for assigning an individuals timecard towards a piece of equipment through Payroll if you are doing in house repair, Assignar handles this in a very strong manner. 

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.