Is there any way to add a change request to an existing subcontract commitment?

It seems I can only add to change order and create a new commitment purchase order.

Thanks

Michael


2 replies

Userlevel 1

Here’s what I would do…..

  1. Go to Construction / Change Orders
  2. Create a new Change Order
  3. Select the Class
  4. Select the Project
  5. Click the “Commitments” tab
  6. Click “Select Commitments”
  7. Select the subcontract you want to change and click “Add Lines & Close”
  8. Enter the amounts, remove hold, and release.

Hope this helps.

Userlevel 3
Badge

Hello @msw21,

Thanks for the post. I am in 100% agreement with @Colm Lennon’s reply above. This should allow you to perform the exact tasks you stated the need to do. If you have any questions, please ask.

Regards,

Mike 

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.
© 2008 — 2020  Acumatica, Inc. All rights reserved