MRP, Linked Sales Orders and Scheduled Production


Forum|alt.badge.img

My client links all sales order to production. Each sales order line has a promise date and ship date. The ship date is the date that production needs to be completed. They are using APS to schedule production which is properly using the ship date as the finish on constraint prior running the scheduling operations.

The issue is MRP is still using the ship date as the promise date resulting in a shortage of materials for scheduled production. How do we get MRP to look at the scheduled production to properly identify material requirements?

We are on 23R1  - 23.110.0025

Best answer by frankfiorentino81

Nevermind. I figured it out. It was the use fixed manufacturing times checkbox on production orders.

View original
Did this topic help you find an answer to your question?

2 replies

Forum|alt.badge.img

Nevermind. I figured it out. It was the use fixed manufacturing times checkbox on production orders.


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • 2759 replies
  • October 19, 2023

Thank you for sharing your solution with the community @frankfiorentino81!


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings