Trying to get a business event to trigger once a week, however, the process doesn’t seem to be working. The Automation Schedule is running, but the business event itself is not. Any troubleshooting ideas?




Trying to get a business event to trigger once a week, however, the process doesn’t seem to be working. The Automation Schedule is running, but the business event itself is not. Any troubleshooting ideas?
Best answer by lauraj46
Hi
The post below contains a step-by-step guide on how to configure a scheduled report using a business event. It’s a bit old, but I think it still accurate. I would suggest reviewing this info to a verify that your setup is correct. If you’re still having issues, please upload the XML for your business event and GI.
Hope this helps!
Laura
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.