We currently operate a cutting location where aluminum bars are cut into different pieces. As we plan to enable the Manufacturing Module in a couple of months, we are seeking advice on the best process to record these transactions in the interim.

Should we utilize Inventory Adjustments and include scrap in the adjustments? We are looking for insights and best practices from the community.

Thank you in advance for your advice!

Best answer by craig2

Hi @aborisova37 ,

Have you explored using Kit Assemblies?  We have a scenario where product gets sent to a third party to be reorganized and packaged, which also results in some shrink.  The carrying costs in the system inflate appropriately, as long as we keep things extremely simple (1 Input, 2-3 Outputs).

Might be worth exploring, best of luck.

View original
Did this topic help you find an answer to your question?

2 replies

craig2
Pro I
Forum|alt.badge.img+3
  • Pro I
  • 100 replies
  • Answer
  • December 18, 2023

Hi @aborisova37 ,

Have you explored using Kit Assemblies?  We have a scenario where product gets sent to a third party to be reorganized and packaged, which also results in some shrink.  The carrying costs in the system inflate appropriately, as long as we keep things extremely simple (1 Input, 2-3 Outputs).

Might be worth exploring, best of luck.


aborisova37
Semi-Pro I
Forum|alt.badge.img+1
  • Author
  • Semi-Pro I
  • 62 replies
  • December 19, 2023

Thank you, @craig2. This might be a good option for us as well.