Finding transactions that haven't been recorded against a subcontract

  • October 16, 2024
  • 1 reply
  • 42 views

Forum|alt.badge.img

We’ve had contracts set up after a number of bills have been entered so I now have a mix of costs in a cost code - some recorded to a contract and some not.

Since the contract was set up for it’s full value I now have open commitments that will never be release.

I’m trying to find a query or a report that will show me all of the transaction for a project/cost code AND include the subcontract number for each line.  Once I’ve identified transactions that should have been part of the contract I can enter a reclassing entry reducing the amount recorded without the contract and increasing the amount billed to the contract.

Here’s the kicker, I can’t find the subcontract number captured in PMTRAN nor GLTRAN.

Besides the billing screen of the project, the only other place I see the subcontract is on the bill input screen.

Can anyone point me to where this data is stored?

Best answer by eucciferri35

The subcontract number is on the APTran Table. I don’t know of an existing report that will show you what invoices don’t have a subcontractor#.  You could create a new generic inquiry by adding the APTran table to the existing Bills and Adjustments GI then you could add the subcontract reference# and project field.  You would then be able to either add conditions where it only pulls the AP bills that have a project# in the project field and subcontract field is empty.

View original
Did this topic help you find an answer to your question?

1 reply

Forum|alt.badge.img
  • Jr Varsity III
  • 17 replies
  • Answer
  • October 17, 2024

The subcontract number is on the APTran Table. I don’t know of an existing report that will show you what invoices don’t have a subcontractor#.  You could create a new generic inquiry by adding the APTran table to the existing Bills and Adjustments GI then you could add the subcontract reference# and project field.  You would then be able to either add conditions where it only pulls the AP bills that have a project# in the project field and subcontract field is empty.