All,
We are new to Acumatica, and we are running into an issue when we have to reverse a progress billing. We reversed it using the Proforma, not the AR function, and applied the credit memo as we have been trained. The issue we have now is when we try to rebill the project, the system reflects the percent billed that we reversed and we cannot correct it. We need the ability to reverse and later rebill the same percentage without issue. Has anyone else run into this issue? If so, how did you correct it?