Skip to main content
Solved

Project - Uploading Schedule of Value Description and Values


Forum|alt.badge.img

Is there a way of uploading my Project schedule of Value AIA g703 “Description and Value” Instead of adding each line item one by one?

 

Best answer by Laura02

Hello @gracef ,

I think the easiest way to plan the Excel File layout is to export directly from Project Revenue Budget tab, yes.  Then populate your sheet, for each project.

Import from File will import the first tab of an Excel file to your project.

Good luck!

Laura

View original
Did this topic help you find an answer to your question?

4 replies

Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • April 22, 2024

Hello,

Schedule of Values may be imported from Excel one project at a time using Load from File button.

Schedule of Values may be imported for many projects at once using Integration →  Import Scenarios.

Laura


Forum|alt.badge.img
  • Author
  • Freshman I
  • 10 replies
  • April 23, 2024

Thank you Laura, So since my Schedule of Value is different format. Should I just go to Project Revenue Budget, and export to excel then add my info form my Schedule of Value correct. Is this the best way?


Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • Answer
  • April 23, 2024

Hello @gracef ,

I think the easiest way to plan the Excel File layout is to export directly from Project Revenue Budget tab, yes.  Then populate your sheet, for each project.

Import from File will import the first tab of an Excel file to your project.

Good luck!

Laura


Forum|alt.badge.img
  • Author
  • Freshman I
  • 10 replies
  • April 23, 2024

Perfect Thank you!