Over Produced a Production Order - Best practices to Correct


Forum|alt.badge.img

We have an issue where our team processed a production Move transaction for the incorrect qty. Finished goods is now overstated and raw/pack understated. What is the best way to return and deconstruct some of that product to reduce our FG and increase the Raw/Packs?

3 replies

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • 819 replies
  • July 3, 2023

Have you closed the Production Order?  If not, you can create/release a move transaction for a negative quantity to pull the production item back out of inventory into the production order to make adjustments.


Forum|alt.badge.img
  • Author
  • 74 replies
  • July 3, 2023

That is typically what we have done in the past. What is the best way to clear the corresponding receipt and Return? Just bill them at an ext cost of 0 and let the expense/credit book to the P&L?


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • 2754 replies
  • July 24, 2023

Hi @byates were you able to find a solution? Thank you!