We would like to see the ability to report prior period WIP reports that include open commitments and change orders by period. Another way of saying this is period sensitive reports for POs and COs.
Solved
Project Change Order and Commitment reporting by period
Best answer by gprice27
Hello - we have been able to achieve this on the WIP by Date Range - by adding additional subreports
We have also added Cost Projections (Projected Cost at Completion) using a sub report.
It would be nice to have these available in the standard WIP reports.