Skip to main content
Solved

Multiple Invoices created when "Release Retainage" action is run. It should be a single final Invoice


Looking for tips to get our final “Release Retention” to create only a single final invoice.  Right now the system is looking at the Unreleased Retention on all previous Project Invoices and creating an Invoice for each one.  Wondering if this is a setting issue or a process issue?

 

 

Here you see it creates two separate invoices 

 

Best answer by rlaaguid81

I had the same issue. I enabled “Payment Application by Line” feature. Now the AR retainage release generates a single invoice.
 

View original
Did this topic help you find an answer to your question?

6 replies

Heidi Dempsey
Community Manager
Forum|alt.badge.img+2
  • Community Manager
  • 269 replies
  • July 30, 2024

@KShepherd  Thanks for the question.  The Consolidated retainage invoice functionality was introduced in 23R2.  What version are you on?


rlaaguid81
Freshman II
  • Freshman II
  • 1 reply
  • Answer
  • August 1, 2024

I had the same issue. I enabled “Payment Application by Line” feature. Now the AR retainage release generates a single invoice.
 


  • Freshman I
  • 2 replies
  • September 4, 2024
rlaaguid81 wrote:

I had the same issue. I enabled “Payment Application by Line” feature. Now the AR retainage release generates a single invoice.
 

Can you confirm what version you were able to use this workaround on?


Forum|alt.badge.img
  • Freshman II
  • 10 replies
  • December 5, 2024

Checking to see that since this feature was enabled to form only one invoice if anyone else noticed that now when a payment is applied to that retainage invoice, it closes the retainage invoice but leaves the original invoice open?  I just sent a support request in because none of the original invoices where the retainage was taken from are closing.


Heidi Dempsey
Community Manager
Forum|alt.badge.img+2
  • Community Manager
  • 269 replies
  • December 6, 2024

@kgawryluk80 I see your case and we will take a look for you.  

This is the expected behavior-

Status of original document included into consolidated retainage document shall be changed to Closed if all of the following conditions are met (this is existing logic):

  • balance of the original document is 0 (if document has Pay by line = TRUE + balance of document lines = 0)
  • unreleased retainage of the original documents is 0
  • unpaid retainage is 0 

  • Freshman I
  • 1 reply
  • December 10, 2024

I just sent your suggestion to ACU support because they are stating I need to Recalculate Customer Balances however we did this years ago when trying to fix a huge retainage issue and it really messed up our financials.  Can you tell me how to apply the logic you are suggesting up top?  I would have to give the information to our IT person(I usually submit tickets under his user name) but he is not sure either on how to fix this problem.  

THanks, 