Can APS schedule substitute work centers?


We have a client that has multiple production lines that they can choose from to perform the same operation. I am trying to use APS to automatically fill the capacity of these lines. 

As of yet I have not found a suitable solution to achieve this. 

Does anybody have some advice here? 

 

Best answer by angierowley75

There is work center substitution capability within Acumatic MFG APS.

https://help.acumatica.com/(W(43))/Help?ScreenId=ShowWiki&pageid=c0b2f338-88f0-4ab0-8b4b-222526a5bf25

 

However the APS algorithm currently does not support scheduling multiple assembly lines / splitting capacity for production across a group of work centers.  We rely on Vendor Solutions to provide this advance scheduling capability.

View original
Did this topic help you find an answer to your question?

2 replies

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • 848 replies
  • Answer
  • November 8, 2023

There is work center substitution capability within Acumatic MFG APS.

https://help.acumatica.com/(W(43))/Help?ScreenId=ShowWiki&pageid=c0b2f338-88f0-4ab0-8b4b-222526a5bf25

 

However the APS algorithm currently does not support scheduling multiple assembly lines / splitting capacity for production across a group of work centers.  We rely on Vendor Solutions to provide this advance scheduling capability.


  • Author
  • Freshman II
  • 2 replies
  • November 13, 2023

Hi @angierowley75, thank you for your reply. I will investigate the solutions available.