I need a report that will show total hours worked, by construction project, by employee, for a specific date range.  There are only two canned hours reports in the construction edition -- neither of them accomplish what I am looking for.

I’ve built a generic inquiry from the Earning Details screen and made a pivot table - which is okay -- but I’d rather have a standard report I can run each month.

Any suggestions?

Hi @ashtonwilliams96 

I dont see an out of the box report that has date range option. You may customize one of those two reports available now to add the date parameter. They pull activity detail from PMTimeActivity table which has date information.

  • Employee hour : ScreenID PM622000
  • Employee hours by Project and Task : ScreenID PM623000

Hope this helps.