This may be simplicity, but I honestly cannot figure this out. I created and released the below Production Order:
And I’m seeing it on the Schedule Board, but it’s not taking up any capacity in the Production Schedule Board. What am I doing wrong? I have the BOM, routing, and calendar all set up
Best answer by ericwolfe74
After creating the production order did you Perform APS Maintenance (form AM512000)?
Update Work CenterSchedule from Calendar
Cleanup History
I also like to schedule the production orders on the Rough-Cut Planning screen (form AM501000)
Clear the Exclude Planning Orders and/or Exclude Firm Orders if you do not want these type orders included in the Rough-cut planning.