Getting unexpected results.  Anyone have any insight they can share?

Both planned and actual labor are incorrect
 

 

Best answer by angierowley75

Please log a case with support so they can investigate why you are receiving unexpected results.

View original
Did this topic help you find an answer to your question?

4 replies

Forum|alt.badge.img+6
  • Author
  • Captain II
  • 279 replies
  • May 31, 2024

Updated with this image to point out overhead in this image.

So I have 2 issues.  The labor costs above, and the actual overhead in this image.

 


angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • 790 replies
  • Answer
  • May 31, 2024

Please log a case with support so they can investigate why you are receiving unexpected results.


Forum|alt.badge.img+2

@ltussing03  You should check whether labor rate it updated in the database?
I ran a quick test and had updated labor rate. If you added a labor line before updating the Labor rate then system won't update the rate until you reselect the employee to update it. 


Forum|alt.badge.img+6
  • Author
  • Captain II
  • 279 replies
  • May 31, 2024

Pragati, thanks.  The labor rate was not changed.