Hello,
We have multiple warehouses. All sell/MFG the same products. We’d prefer not to have a BOM for each warehouse since they are all the same. However, when I regen MRP after entering a sales order, I get different results if the warehouse on the sales order differs from warehouse on the BOM.
Example:
Finished product with 4 different materials.
- Enter a sales order for the finished product using the warehouse on the BOM.
- Regen MRP
- MRP Display suggests a production order for the finished product AND purchase suggestions for the materials (this is the desired behavior)
- Enter a sales order for the finished product using a warehouse NOT ON THE BOM.
- Regen MRP
- MRP Display ONLY suggests a production order for the finished product. It does NOT suggest anything for the needed materials.
I have tried using substitution work centers and see no difference in behavior.
Again, I am just trying to avoid having 7 different BOMs for the same finished part just because it is being made in a different warehouses.