Hello, in production:
If I have a work step (0020), the next work step (0030) has a completed quantity, but it is not yet completely finished.
And then I want to change the description or the setup time in work step 0020, for example. An error occurs. (Shown in the image)

If I have changed an entry and then click on another field or save, the following error message appears and the system deletes the operation ID.
#but if the following work step does not contain a completed quantity, I can change everything.
Is that normal or is it a bug?

 

initial Situation
Error Message

 

Best answer by PragatiMalviya64

@SchellerFer It depends on the next operation, if the next operation is “In Process”, then system will not allow you to edit the description. 
So, in your scenario, you can modify description in the work step (0030) because work step (0040) is not in Process state. 

Although, error location and error itself should be improvised. Can you please submit support ticket for it?
 

View original
Did this topic help you find an answer to your question?

1 reply

Forum|alt.badge.img+2

@SchellerFer It depends on the next operation, if the next operation is “In Process”, then system will not allow you to edit the description. 
So, in your scenario, you can modify description in the work step (0030) because work step (0040) is not in Process state. 

Although, error location and error itself should be improvised. Can you please submit support ticket for it?
 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings