Hi 

 

I have been trying to set up CTP with a multi-level BoM and I am having some trouble.

 

Does anyone know if CTP work with multi-level BoMs please?

 

Thanks

 

Matt

 

Best answer by jdobish

To my knowledge, it does not go down more than 1 level. 

View original
Did this topic help you find an answer to your question?

3 replies

jdobish
Pro II
Forum|alt.badge.img+2
  • Pro II
  • 230 replies
  • Answer
  • November 16, 2021

To my knowledge, it does not go down more than 1 level. 


Forum|alt.badge.img
  • Freshman II
  • 19 replies
  • March 25, 2022

I hope Acumatica is addressing this.  Lets look at an example of how it works at the moment:

Sales order that has rows for the following:

  • Stock items that are purchased
    Does not work so if you have insufficient stock for a purchase item you have no idea when it can be in stock
     
  • Items with single level BOMs
    The only rows where you can get a reliable result
     
  • Items that have multi-level BOMs that are assemble to order
    If you have stock of the subassembly then you are OK.  The whole idea of ATO is to reduce time to delivery.  But if insufficient stock of the subassembly then it Errors.
     
  • Items that are multi-level make to order.
    Fails if there is insufficient stock of any subassembly

So CTP fails 75% of the time.


sdeforge14
Freshman I
Forum|alt.badge.img
  • Freshman I
  • 19 replies
  • March 18, 2025

Hi There,

 

We are in the need of this as well, although a workaround would be to duplicate the BOMs as a CTP type bom and instead of true subassemblies you could use Phantoms as a work around? 