I have a scenario i want to create to update open Production Orders. I have an XLS that has the Production order number, the Operation, the Work Center, the current Overhead Rate, and what the New Over Rate should be.
I need to do this from screen AM209000.
The steps would be to look up the Production Order, Place the order on Hold, and select the proper operation. next, you would have to update the Overhead factor on the Overhead tab to the “New Rate” and take it off hold save. From here you would progress to the next item on the list.
Screen AM209000
Any thoughts??
Best answer by Evan Templin
View original