Solved

UPDATE ERROR to Purchasing Receipt Form

  • October 24, 2024
  • 7 replies
  • 73 views

cwilliams23
Freshman I
Forum|alt.badge.img

This is the screen prior to the October, 2024 update of our Purchasing Receipt form. The TOTAL COST - was included and we used it to verify the invoice amount. They have since removed it from the Sandbox - does anyone have a fix. 

 

There is no way to verify the amount of the entered invoice(receipt)- some our invoices have over 100 lines and not all the lines on the PO are included - backorders, etc... I understand why they might think that it was helpful to remove it - but for those of us who require it to balance the cost of goods it is a real problem. 

Any solution?

Best answer by GJensen

We have a customer that exclusively uses sales orders with drop shipment purchase orders.  Having this field show the purchased cost is a huge time saver.  Rather than removing the field why not make it a preference so customers that have built a process around the screen can continue to work as they have in the past.

View original
Did this topic help you find an answer to your question?

7 replies

Manikanta Dhulipudi
Captain II
Forum|alt.badge.img+13

@cwilliams23 Total cost filed is invisible in the code you can ask developer to enable it with a small customization.

 


Forum|alt.badge.img+2
  • Jr Varsity III
  • 43 replies
  • October 24, 2024

A little bit more on the Total Cost field in Purchase Receipt:

The Total Cost has been removed from the Purchase Receipt header on the 2024R1 version.

Please see below a link to the Release Notes for more information:

https://acumatica-builds.s3.amazonaws.com/builds/24.1/ReleaseNotes/AcumaticaERP_2024R1_ReleaseNotes_Other_Enhancements.pdf

Our development team has removed this field since Purchase Receipt is not a financial document and all financial information has been excluded from this form. 

This field was not recalculating if the cost or quantity was changed in any line which had a discount applied. Only an approximate value was displayed. 

Vendor bills will have exact amounts of the PO.

 

 

 


cwilliams23
Freshman I
Forum|alt.badge.img
  • Author
  • Freshman I
  • 12 replies
  • October 24, 2024

The actual amount was recalculating to the correct amount when any discount or changes were applied. The correct amount of the invoices was shown in the Total Cost field. We bill by project not by product. 

It is assumptive that vendors always have the correct amount on the bills. At least 20% contain incorrect pricing. I could list the reason, however we use it for cost verification. 

Can you please tell which section specifically states the deletion in the form.

 


GJensen
Freshman II
  • Freshman II
  • 43 replies
  • Answer
  • November 4, 2024

We have a customer that exclusively uses sales orders with drop shipment purchase orders.  Having this field show the purchased cost is a huge time saver.  Rather than removing the field why not make it a preference so customers that have built a process around the screen can continue to work as they have in the past.


cwilliams23
Freshman I
Forum|alt.badge.img
  • Author
  • Freshman I
  • 12 replies
  • November 4, 2024

We also use it to verify the RTV costs when returning material to the vendor. I hope that it will be optional as it was a valuable asset!

 


  • Freshman I
  • 2 replies
  • November 14, 2024

@SheriThomas49 @Manikanta Dhulipudi I have the same problem, and need a fix. Suggestions? Person entering POs and person receiving POs do not have the same process logic and access, so they cannot verify if totals match between PO and Receipt. Also, revising POs all the time is not a viable solution, especially with Drop-ship links, and any case of shortages or incorrect pricing due to a human error or other reason.

Please advise.


  • Freshman I
  • 1 reply
  • November 14, 2024

We would like to have the total cost added back to PO Receipts as well.  I understand that the PO Receipt is not a financial document but it is creating a financial document in the form of a Vendor Bill in Payables.  If the cost on a PO Receipt is changed, the Bill is generated using that cost, not the cost on the Purchase Order.  

Perhaps it would be better to make the cost field on PO Receipts uneditable so the PO cost is what is used to generate the Bill, while at the same time, allowing the user processing the PO Receipt to verify the total cost on the vendor invoice received.  Our SOP would instruct the user entering the PO Receipt to keep the PO Receipt On Hold if the Total Cost does not match and inquire with the purchasing agent to research any discrepancy prior to the Bill being generated.. 


Reply