Cost Budget tab in project - actual hours and amount not updating properly


Hi, 

I have been facing issues where employee working time against project is not updating correctly under Cost Budget tab. 

Few checks done -

GL Accural Account under Project and Expense Accural Account for Non Stock Item are same. It belongs to Labour Account group

UOM is displayed same for Project transactions and on Cost Budget line.

When employee enters hours for project, Actual qty is not updated. It still displays 0

Recalculate Project balances does not affect. 

 

Please help.

12 replies

Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • March 6, 2024

Hello,

What is the status of the Time Activity and/or Timecard?

 

Laura


  • Author
  • Freshman I
  • 7 replies
  • March 6, 2024

Hi Laura, 

Time Activities are released. 

 


Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • March 6, 2024

Hello,

As soon as an Activity or Timecard is released, we should see the actual amount and hours on the project.

If you place your cursor on the Labor task of the project and click View Transactions… can you see the transactions?

 

Can you show the released transactions in Project Transactions screen?

Laura


  • Author
  • Freshman I
  • 7 replies
  • March 6, 2024

Hi Laura, 

I can see the released project transactions 

 


Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • March 7, 2024

Hello, 

I’m not sure I know the answer. Did project time once work; did it successfully update your projects before and then something changed to cause it not to work?

Or do some projects still work correctly and this one project does not work? 
 

Is your site customized? If your site is customized, do you experience the same behavior when time is released while customizations are temporarily unpublished?

Thank you.

Laura


  • Author
  • Freshman I
  • 7 replies
  • March 7, 2024

Hi Laura, 

 

It never worked. Even the site is not customised. I am not sure what is missing. 


  • Author
  • Freshman I
  • 7 replies
  • March 18, 2024

Was able to resolve it. Thanks


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • 2750 replies
  • March 19, 2024

Hi @BellaGandhi - Can you share your solution with the community? Thank you!


parveza33
Jr Varsity III
Forum|alt.badge.img
  • Jr Varsity III
  • 15 replies
  • October 9, 2024

@BellaGandhi  Please share the solution, I am too facing the same Issue.


  • Freshman I
  • 1 reply
  • March 10, 2025

Hi All, I had this same issue and the cause was the UOM missing on the cost budget line. Adding the UOM and running a re-calculate fixed this and the Actual Qty appeared. 


  • Freshman I
  • 7 replies
  • March 13, 2025
mbelkin wrote:

Hi All, I had this same issue and the cause was the UOM missing on the cost budget line. Adding the UOM and running a re-calculate fixed this and the Actual Qty appeared. 

@mbelkin, Super helpful! Thanks for sharing.


  • Freshman I
  • 7 replies
  • March 13, 2025
mbelkin wrote:

Hi All, I had this same issue and the cause was the UOM missing on the cost budget line. Adding the UOM and running a re-calculate fixed this and the Actual Qty appeared. 

My issue related to UOM not showing up related to a Change Order. Is there a reason it wouldn’t write back to the Cost Budget? Maybe because the Cost Budget Level is set to Task and Item (the CO does not have an item associated)?