Hi,

I'm experimenting with moving transactions from Project A to Project B.
However, as soon as I enable POST transaction to GL, it gives me an error.
Yet the project and tasks exist, and the accounts in the original transaction belong to account groups.

 

As a trial and error, I tried to do the following for the accounts:

[debit account]  & [credit account] 
"use source" & "use source",
"use source" & "Debit source"
"Credit source" and "use source",
"Debit source" "Credit source"
This didn't work either way.

What am i doing wrong?

 

 

 

 

 

Best answer by raphrf

Hi, my other problem is this one :

I created allocation rule in order to reallocate transaction from projet 17 to the project 16. I setted the allocation rule on the task ACHAT of project 17, I enabled Run Allocation on Release of Project Transactions on project 17.

I created a PM on project 17,It created a PM allocation.

Problem is:  it hitted the project 16 as it should but it dont credit the project 17. Why? It lack two other row to credit the 17 in the allocation transaction.

 

Thanks for all

 

Allocate From

 

Original PM Transaction

 

Allocation who seem to lack two row for the credit of project 16

 

View original
Did this topic help you find an answer to your question?

3 replies

Forum|alt.badge.img+1
  • Author
  • Pro III
  • 167 replies
  • April 16, 2025

I found the problem, i had extra old existing transaction blocking the allocation (maybe no account group)


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • 2790 replies
  • April 17, 2025

Thank you for sharing your solution with the community ​@raphrf!


Forum|alt.badge.img+1
  • Author
  • Pro III
  • 167 replies
  • Answer
  • April 18, 2025

Hi, my other problem is this one :

I created allocation rule in order to reallocate transaction from projet 17 to the project 16. I setted the allocation rule on the task ACHAT of project 17, I enabled Run Allocation on Release of Project Transactions on project 17.

I created a PM on project 17,It created a PM allocation.

Problem is:  it hitted the project 16 as it should but it dont credit the project 17. Why? It lack two other row to credit the 17 in the allocation transaction.

 

Thanks for all

 

Allocate From

 

Original PM Transaction

 

Allocation who seem to lack two row for the credit of project 16

 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings