Skip to main content
Solved

Time Activities Hold / Completed action


Janella
Jr Varsity III
Forum|alt.badge.img

I can’t find a way to mass remove the hold box - does anyone know if there is a setting somewhere or any mass action to remove hold on Employee Time Activities? 

All we need is the time activities that sync from WFG to be completed and then can use mass action to RELEASE them in screenID EP507020

 

 

Best answer by Kandy Beatty

Hi @Janella 

There is no way to mass un-Hold these. However, I found an idea that you may upvote similar to what you are looking for:

https://community.acumatica.com/ideas/add-option-for-time-activities-from-manufacturing-to-come-over-as-completed-or-add-selection-to-take-multiple-time-entries-off-hold-17029

 

I would suggest that you comment this is needed not just for Manufacturing. 

View original
Did this topic help you find an answer to your question?

3 replies

Kandy Beatty
Captain II
Forum|alt.badge.img+16
  • Captain II
  • 2209 replies
  • Answer
  • July 31, 2024

Hi @Janella 

There is no way to mass un-Hold these. However, I found an idea that you may upvote similar to what you are looking for:

https://community.acumatica.com/ideas/add-option-for-time-activities-from-manufacturing-to-come-over-as-completed-or-add-selection-to-take-multiple-time-entries-off-hold-17029

 

I would suggest that you comment this is needed not just for Manufacturing. 


Janella
Jr Varsity III
Forum|alt.badge.img
  • Author
  • Jr Varsity III
  • 70 replies
  • July 31, 2024

@Kandy Beatty  Hi, gotcha thanks, we came up with a workaround for now just upvoted the idea. 


  • Freshman I
  • 3 replies
  • February 9, 2025

Hi ​@Janella  - would you mind sharing the workaround you used, please? 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings