Hi, we have a subcontract that incurred backcharges for scope that was bought out by another company that ran the subcontract total amount into the negative. We recently changed our ERP to Acumatica and we are looking to track this backcharge but cannot process the change orders that run the subcontract into the negative.
How can I track this negative commitment amount for my project buyout summary?
ex. Subcontract A issued for $5,000. Subcontractor A failed to perform work and another Subcontractor B bought their contract for $5,100. We need to process a deductive change order for the buyout amount to accurately track the money owed to us by Subcontractor A for the increased cost of Subcontractor B.