PROJECT BALANCES - OPEN COMMITTED AMOUNT >0 WITH ALL ORDERS CLOSED


Forum|alt.badge.img+1

Hi,

We dont understand why we have an amount here , all the commitment are closed/clompleted ?

ssssws

 

 

 

What is the condition in order to be part of this total?

Thanks

4 replies

mike.gillum
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Moderator
  • 96 replies
  • March 17, 2025

@raphrf Have you tried running the Recalculate Project Balance function from the Project Actions Menu? I’ve seen this address this issue. 

 


Forum|alt.badge.img+1
  • Author
  • Semi-Pro III
  • 153 replies
  • March 17, 2025
mike.gillum wrote:

@raphrf Have you tried running the Recalculate Project Balance function from the Project Actions Menu? I’ve seen this address this issue. 

 

Hi tried it without success

I got all this amount into 1 account group

 

 

if I click on View Commitment i have this 

one row is this one

 

the item was returned so it’s logic, is there something we are doing wrong?

how to correct this in the “good way”?


Forum|alt.badge.img+1
  • Author
  • Semi-Pro III
  • 153 replies
  • March 17, 2025

In order to correct this PO, i tried this without succes :

On the line of the PO I cannot tick Cancelled because we already have reception/return

 


aaghaei
Captain II
Forum|alt.badge.img+10
  • Captain II
  • 1203 replies
  • March 26, 2025

Hi Raph,

To me it seems like a system glitch. In my opinion when a PO/SC is completed/Closed, even if there is unbilled quantity/amount, the system should adjust the Project Commitment to read zero open committed quantity/cost for the associated PO/SC either by revising the existing commitment record or generating an adjusting transaction (i.e. “Commitment Close-out” type transaction) tied to the original commitment record.


Reply