Have a question on how to deal with change order costs:
I will use an example of a time and material ticket. We have a dummy cost code setup for change order costs that happen before an approved change order is processed. Therefore, we have a dump code that is accruing change order costs and then I’m going in and entering the cost budget side AGAIN when the change order gets approved. Not only now am I doubling the costs but Acumatica does not know that the costs in the dump code are related to a change order - it’s getting bundled into the original cost budget.
How can I handle this so that these costs can at least go towards the change order after the fact?