Change Order Cost - what period to they hit


Forum|alt.badge.img

I’m recording a change order to impact costs but I can’t seem to control what period they are reflected in on the Project Cost Reports.  

I’ve set both the Change Date & the Approval Date to 7/31/2023 but when I run the Project Cost Report the change only shows if I run it for the period 8/31/2024 (the current period).

I need to be able to see this change reflect in the prior year’s period (July 2023).

I don’t see a finperiod on the change order.  That’s why I assumed it would be driven by the Change Date or the Approval Date.

 

Best answer by aaghaei

@RHarrison @meganfriesen37 also I believe it is a great product idea so TranPeriodID and FinPeriodID is added to this screen. If you like please create a Product Idea and share the link so people can upvote. In my view any screen that has financial impacts should be bound to the PeriodIDs.

View original
Did this topic help you find an answer to your question?

7 replies

meganfriesen37
Captain II
Forum|alt.badge.img+11

What version of Acumatica are you on?  I know that we’ve run into a few issues on the WIP reports and others around the dates on the change orders and what period they get included in.  Also - do your periods follow the calendar year (i.e. January is period 1) or do you have a non-calendar fiscal year (i.e. Fiscal year starts in March or something).  Our issues were partially due to a non-calendar fiscal year, but we had to submit a case to Acumatica and I think they were able to get this fixed in a later build but may have given my colleague an updated version of the report in the interim.

Cases 317999 - Relates to Known Issue AC-286348, fixed in 23.112 - Items posted on the first or last day of the period posted into an incorrect period.
 

Case 303128 - Issues in 22.113 (prior to upgrade) around the non-calendar fiscal year (i.e. items with a date in April (period 07-2023) were displayed in the reports as posted into period 04-2023, even though for the client that was the January period)

 


Forum|alt.badge.img
  • Author
  • Freshman I
  • 35 replies
  • August 12, 2024
meganfriesen37 wrote:

What version of Acumatica are you on?  I know that we’ve run into a few issues on the WIP reports and others around the dates on the change orders and what period they get included in.  Also - do your periods follow the calendar year (i.e. January is period 1) or do you have a non-calendar fiscal year (i.e. Fiscal year starts in March or something).  Our issues were partially due to a non-calendar fiscal year, but we had to submit a case to Acumatica and I think they were able to get this fixed in a later build but may have given my colleague an updated version of the report in the interim.

Cases 317999 - Relates to Known Issue AC-286348, fixed in 23.112 - Items posted on the first or last day of the period posted into an incorrect period.
 

Case 303128 - Issues in 22.113 (prior to upgrade) around the non-calendar fiscal year (i.e. items with a date in April (period 07-2023) were displayed in the reports as posted into period 04-2023, even though for the client that was the January period)

 

And our fiscal year is the same as calendar years.  So it looks like it’s a reporting issue.  

Which date should the report be picking up?  The Change Date or the Approval date?

 


meganfriesen37
Captain II
Forum|alt.badge.img+11

Based on the release notes for the known issue, I think it’s the approval date.  Since this is posting back into an older period, have you tried recalculating the project balances?


Forum|alt.badge.img
  • Author
  • Freshman I
  • 35 replies
  • August 12, 2024
meganfriesen37 wrote:

Based on the release notes for the known issue, I think it’s the approval date.  Since this is posting back into an older period, have you tried recalculating the project balances?

Yes, I’ve recalc’d the project balances.

It’s strange that I set both the approval date and Change Date as 2023.


meganfriesen37
Captain II
Forum|alt.badge.img+11

Maybe log a case with Acumatica.  It could be that there’s something hardcoded into the background that’s taking the actual time/date stamp from the approval from this week and preventing it from being back-dated?


aaghaei
Captain II
Forum|alt.badge.img+9
  • Captain II
  • 1178 replies
  • Answer
  • August 13, 2024

@RHarrison @meganfriesen37 also I believe it is a great product idea so TranPeriodID and FinPeriodID is added to this screen. If you like please create a Product Idea and share the link so people can upvote. In my view any screen that has financial impacts should be bound to the PeriodIDs.


meganfriesen37
Captain II
Forum|alt.badge.img+11

Reply