Budget Transfers Between Construction Projects?


Forum|alt.badge.img

Wondering if there’s a formal way to transfer cost from one job to another?  We have a subcontractor that is adding $100K to one project and deducting $100K from another.  wondering the best way to do that. 

Best answer by greghall01

Hi Katie - We would probably issue a deduct CO to the sub on one job and issue an add CO on the other job. We would also enter a budget adjustment on each job for their particular budget line (I’m not sure where you would put the other half of the budget change...we tend to use a Contingency cost code for these changes). We would next create an invoice and credit memo for the sub (unless the sub is issuing you an invoice for one job and a credit memo for the other job) and enter those into AP against their subcontracts. I believe that would get everything entered appropriately. Thanks, Greg

View original
Did this topic help you find an answer to your question?

3 replies

  • Freshman II
  • 2 replies
  • Answer
  • July 26, 2022

Hi Katie - We would probably issue a deduct CO to the sub on one job and issue an add CO on the other job. We would also enter a budget adjustment on each job for their particular budget line (I’m not sure where you would put the other half of the budget change...we tend to use a Contingency cost code for these changes). We would next create an invoice and credit memo for the sub (unless the sub is issuing you an invoice for one job and a credit memo for the other job) and enter those into AP against their subcontracts. I believe that would get everything entered appropriately. Thanks, Greg


Laura02
Captain II
Forum|alt.badge.img+19
  • Captain II
  • 3132 replies
  • July 26, 2022

Hello @katiedavison,

You mention transferring cost. Are the budgets for the two jobs changing?  Or did a subcontract vendor invoice you for the incorrect job?  Is the AP Bill already paid (correctly compensating the vendor)?

If the AP is correct (GL is correct too) and the project budgets are correct, and it’s only the COST that needs to be moved from one project to another, you can use Project Transactions screen with a negative entry to the first (incorrect job) and a positive entry to the proper job where the cost belonged. In this case, leave debit and credit account/subaccounts blank on the 2-line Project Transaction.  Entering a negative to incorrect job and positive to correct job will move the cost to the correct project in Projects module with no impact on AP, vendor, or GL.

 


joelhoffman
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Moderator
  • 289 replies
  • July 27, 2022

Adding to what @greghall01 and @laura01 mentioned, if the AP Bill hasn’t been paid and it’s simply an update to the detail lines where the vendor bill needs to be applied, we added an AP Bill Reclassification process in 2021 R2 that allows modification to Project/Task/Cost Code, and we added the same ability for GL Transactions.

Based on your situation, AP Bill Correction, Subcontract Document Revisions, Project Budget Adjustments, Change Order Audit, etc. there are several options available, as you can see within our answers.  If you have a different scenario, let us know and we’ll be happy to walk through additional details.

Thank You.