Anyone took an ISV for Estimating / Project Quote? (redteam, Topbuilder, Proest, Procore, ect)

  • October 24, 2022
  • 6 replies
  • 148 views

Forum|alt.badge.img+1

Do you use the Project Quote in Acumatica or you use a ISV? Do you like it?

Thanks

Best answer by joelhoffman

@raphrf 

What components of the estimate/quote are you looking for suggestion?

There is the Takeoff / Quantity portion, that would then feed into the line item estimate, or there could be a simple Project Quote (no plan takeoff needed), that feeds into the Project Cost/Revenue Budgets.

ProEst would handle both Takeoff/Estimate/Quote and when the project is awarded, feed into Acumatica.  The others mentioned (Procore, Redteam, Topbuilder) have components of each.

It may also be helpful to understand your specialty/concentration.  As @pchappell19  mentioned, depending on the Database/Catalog available, estimating solutions will vary (e.g. Homebuilder, GC, Specialty, Civil).

View original
Did this topic help you find an answer to your question?

6 replies

Forum|alt.badge.img
  • Freshman II
  • 18 replies
  • October 24, 2022

If they truly need take-off and database-based estimating we recommend ProEst unless they are a subcontractor that needs something more specific for their needs (HVAC, Electrical, Earthwork come to mind).


Forum|alt.badge.img+1
  • Author
  • Pro III
  • 167 replies
  • October 24, 2022
pchappell19 wrote:

If they truly need take-off and database-based estimating we recommend ProEst unless they are a subcontractor that needs something more specific for their needs (HVAC, Electrical, Earthwork come to mind).

Hi Pchappell19, Thanks for your answer!

You use Proest personnaly? Why dont use it for a subcontracter?


Forum|alt.badge.img
  • Freshman II
  • 18 replies
  • October 24, 2022

Yes...Per my note above, some subs need additional functionality ProEst doesn’t provide.  For example, it doesn’t do cut/fill quantities for earthwork.


Forum|alt.badge.img+1
  • Author
  • Pro III
  • 167 replies
  • October 27, 2022

No person use Procore here ?


joelhoffman
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Moderator
  • 296 replies
  • Answer
  • October 31, 2022

@raphrf 

What components of the estimate/quote are you looking for suggestion?

There is the Takeoff / Quantity portion, that would then feed into the line item estimate, or there could be a simple Project Quote (no plan takeoff needed), that feeds into the Project Cost/Revenue Budgets.

ProEst would handle both Takeoff/Estimate/Quote and when the project is awarded, feed into Acumatica.  The others mentioned (Procore, Redteam, Topbuilder) have components of each.

It may also be helpful to understand your specialty/concentration.  As @pchappell19  mentioned, depending on the Database/Catalog available, estimating solutions will vary (e.g. Homebuilder, GC, Specialty, Civil).


Forum|alt.badge.img+1
  • Author
  • Pro III
  • 167 replies
  • November 3, 2022

Hi joel, thanks for the answer, relaly appreciated. I sended you a PM 