We are having an issue with the AIA Report (PM644000). When we have the Project Tasks selected to be “Invoiced Separately”, the Main page of the AIA Report is including the entire contract values (all Project Tasks), instead of only including the amounts for each specific project task. The Continuation page is exact & only shows the Project Task that is being invoiced.
Is there an easy way to have the AIA report be project task specific when Invoiced separately is selected?
Let me know if you have a better idea, or need clarification.
Thanks,