I have added a second shift to my work center for 8 hours. My scheduling blocks are set to 1 hour in my Production Preferences. The second shift has its own calendar. I ran the APS maintenance. Then when I look at capacity, the work center shows 40 blocks of capacity. It showed 40 blocks when I had one shift. Now that I have added a shift I would have expected the capacity of this work center to increase to 80 blocks per week.
I have deleted work centers, re-added them, recreated calendars and runt he APS process each time and nothing changes?
Best answer by Debbie Baldwin
View original