When a sub-component production order is created from a parent production order, there is a relationship created on the detail line of the parent to the supply production order:

Is there any way to create this relationship other than generating the prodction order from the parent?  For example, if a subcomponent production order is created independently from a parent, can the relationship be added to a parent production order? 

You can create the Production Orders independently and then link them on the References Tab of Production Order Maintenance

 


Thank you @angierowley75 

My understanding is that the link on the REFERENCES is at the header level bur not necessarily to the line of the parent production order.  Is there a way to link at the line detail level other than when the subcomponent production order is created from the parent?

Thanks!