Skip to main content

When a sub-component production order is created from a parent production order, there is a relationship created on the detail line of the parent to the supply production order:

Is there any way to create this relationship other than generating the prodction order from the parent?  For example, if a subcomponent production order is created independently from a parent, can the relationship be added to a parent production order? 

Thank you @angierowley75 

My understanding is that the link on the REFERENCES is at the header level bur not necessarily to the line of the parent production order.  Is there a way to link at the line detail level other than when the subcomponent production order is created from the parent?

Thanks!

Luke


You can create the Production Orders independently and then link them on the References Tab of Production Order Maintenance

 


Reply