what's the best way to get rid of or a process I should do to get rid of qty remaining in a production order when it's in the Completed & closed stage since we can't go back and edit it. In some of the production reports it still says qty remaining when it was scrap. If there’s a way to figure this issue out that would be great since it will help at lot in a reporting.

 

 

@garcimig09 - There is an option to Include Scrap in Completions? What do you have as your Scrap setting? 


@Debbie Baldwin 

I turned on a while back but I want to correct these mistakes that I found.


@garcimig09 - Then probably someone didn’t report those 4 as “Scrap”? 


@Debbie Baldwin That’s why I want to know if theirs a process that I can do to correct that so I can get rid of that remaining status.


@garcimig09 - 🙂 No - once the order is closed you can’t make any changes. With 23 R2 we are introducing a status between Completed and Closed where you could make changes prior to actually Closing the order. 