Hi Community,
I have a requirement to update the project's revised budget based on a cost forecast and it should be subject to approvals.
I have investigated the following options.
- Create a Budget forecast and update the revised budget. This is possible but the budget forecast does not allow it to collect approvals before updating the budgets.
- Create a cost projection and it is subject to approvals. However, it does not update the project's revised budget and it updates the projected budget columns.
- Change Orders are not an option since it is not connected to forecasting.
Do you have any suggestions for me to handle the above requirement?