We are a construction company that uses the Project module, with very detailed Tasks and Commitments for the parts of the project we sublet out.
The quantities of previously billed items from our subs sometimes get adjusted downward by the time the project ends. For example, we pay for the construction bathrooms by the month. The original PO had allotted 6 months and we have been billed by the sub monthly, for 6 months total.
The project ended 1 week earlier and the sub issued a credit for .25 of a month of charges.
I can easily associate the the credit to the project and task line, but I need to associate the Debit Adjustment to the original PO so we can easily see the total bought from that sub for that project by looking at that particular PO History.
I’m also dealing with a price match scenario with those same bathrooms, we have credits (Debit Adj) from the sub to apply to the already released Bills.
Any ideas?
Thanks in advance!
~Audrey