Background:
- We have UKG Ready for Time & Attendance (old Kronos)
- We have UKG Pro for Payroll (old UltiPro)
- We have IDI Contractor Central for job costing, prevailing wage, and certified jobs
- We use cost over cost (input method) accounting for revenue recognition
Problem: what is the best method for accounting for labor costs and payroll costs in Acumatica?
Solution 1:
- Feed timesheet and payroll data to IDI. Have IDI calculate fully burdened project labor costs.
- Upload project labor costs from IDI to Acumatica in an off balance account group that doesn’t hit the G/L
- Upload direct labor payroll and benefit costs from UKG Pro to Direct Labor accounts as journal transactions, NOT project transactions.
- Upload indirect labor payroll and benefits costs from UKG Pro to SG&A via journal transactions.
Solution 2:
- Feed timesheet data (including project / task) to UltiPro for payroll run.
- Upload payroll and benefit costs to SG&A accounts as journal transactions.
- Secondary journal transactions to move from indirect accounts to direct labor accounts. This would include Project / Task to account for Direct Labor to the correct projects.
- Each project would have detailed transactions, including wages, employer burden, and benefit costs.
- No off balance accounts required
Anyone have any experience that they could share? I’m interested in learning what others are doing when they have 3rd party Time / Payroll systems in the mix.
Thanks in advance for any insights.
Colm