Hi @Noah
Using ‘Critical Materials’ (AM401000), one can create Purchase orders for Production components not in stock. Here is the documentation reference you can check :
https://help-2020r2.acumatica.com/(W(6))/Help?ScreenId=ShowWiki&pageid=ddb714c7-ffa5-49b8-a8e6-9e0695a81f37
https://help-2020r2.acumatica.com/(W(7))/Help?ScreenId=ShowWiki&pageid=c321bba2-d7fd-4445-91ea-3d4ec216a572
Hoping to see any other workarounds used by other users. With regards to core requisition functionality is concerned, there is no option to skip bidding. There are a couple of requests posted on our Ideas page in this regard. Here are the links:
Hope this helps,
Regards,
It sounds like you just need to take requisitions out of your process. That is not a required step and like Vkumar indicated, the out of box functionality for normal POs without requisitions sounds like what you want.
Thanks Vijay and Rob.
We are not currently useing requisitions, I have only been experimenting with it in a test environment because it looks so close to the functionality that we need.
The functionality we want is for any employee to mark or select items from our entire line of Inventory as ‘getting low’. I’ve created an ‘Low Stock’ attribute and a Generic Inquiry to display only marked items (in testing). Then we would like to tap into the functionality that requisitions and critical materials has to create multiple Purchase Orders based on the default vendor for each item.
Making purchases from Critical Materials is close as well, but they are tied to a BOM and Production Order. I suppose we could create a BOM with all of Inventory items, but still our purchaser would have to manually ‘Show all items’ then select them based on the ‘Low Stock’ Generic Inquiry.
Anyone know how we can use the methods of Critical Materials and Requisitions to do this? I suppose it might be able to be done with Automation Schedules, Business Events, Import and Export Scenarios...but that is getting really complicated for a feature that feels so close.
The feature set is there, just not great for small companies like us that are still getting their Inventory tracking under control.
Thanks for the replies and any further suggestions!
Have you looked at Prepare Replenishment?
And you might take a look at EasyStock or NetStock.
Dennis, I did stumble upon Prepare Replenishment after I posted this, and I think it’s the way we are going to explore for the time being. EasyStock and NetStock look really nice, but there is no way the boss will go for another product expense. They don’t understand why they’ve been shelling out a ton of money on Acumatica for almost a year and it doesn’t do everything for us automatically already :)….and to be honest, in some cases, especially when it was sold to us as doing so like in this situation, they are right.
Thank you everyone for the replies!! If the Acumatica community was 3-10x the size and had that many more people like you all, work life would be so much better for a lot of us! I hope the higher ups are paying attention that this is where Acumatica growth is hiding!!
not in sales webinars
Have you looked at Prepare Replenishment?
Min max with replenishment or MRP should do the trick