I have a customer who costs EVERYTHING used to manufacture an item (i.e. pallets, bags, box labels, etc.). But a quantity of 1 is used per manufacturing order, not per piece during an operation.

Is there a way to add those items to the BOM without having to have it be a fraction of the item per item produced?

Please help :)

That’s exactly what I’m looking for, thank you so much!


If think you can also try to use 'Batch size' column in Material tab(BOM screen) and set it on 0 for specific material.

 


The only option of which I am aware to capture the cost is to setup it up as fixed overhead.