Hi Everyone,
What is the effect of activating Projects and Tasks and entering invoices before adding the revenue/cost budgets?
Thanks!
Hi Everyone,
What is the effect of activating Projects and Tasks and entering invoices before adding the revenue/cost budgets?
Thanks!
If you are talking about the payable side as soon as you enter an AP Bills which is tied to the project will system will create the cost budget line automatically with zero budgeted cost.
if you are taking about the receivable side, how you are going to create Pro Forna invoice without Revenue Budget lines? You might know a hack that I don’t know :)
We don’t make proforma invoice..
If you don’t do Pro Forma, then you do not expect the system to tie your invoices back to the project's Revenue Budget so the question becomes irrelevant. If you want the tie, you need to go through Pro Forma. It is the whole purpose of Pro Forma existence in addition to progress billing and AIA reports.
Hi
Are you saying without Pro Forma, when you open your project profile and review Revenue Budget lines are figures updated there properly?
And next time when you want to create a bill to your client system automatically brings in the previously invoiced amount for each revenue line?
I don’t have construction edition handy to provide screenshots but the standard construction progress bills that system generate include Revenue Line, the Revised Budget, Completed to Date, Previously Completed and Current Period Amount per Revenue Budget Line in normal settings
But getting back to your original question, if you do not track billed to date figures and include in your bills, then you do not need to worry about setting up your revenue budget before starting the billing
Just like this?
This is project balances tab of projects profile that groups data by Account Group. What I’m talking about is the revenue tab and the actual invoice you send to your clients monthly/periodically.
I feel you need some training so please have your Acumatica Partner or independent consultant do a training/refresher for you.
We just go on live in Acumatica 2 months ago, we are still figudring things out. Our consultant don’t provide enough details and charge us expensive billing. So we are trying to figure out things, do our own trainings and research.
In my previous role, we didn’t update the revenue budget in projects. I was able to generate the invoices and post to the project, report from the project just fine. We also did not use the pro-forma invoices.
Keep in mind, that we did not use any budget to actual reporting on the projects either.
Not sure if this is helpful.
Sorry to hear that about your consultant. It sometimes is the case. Have you read and watched the Acumatica Open University Construction/Project Accounting materials? They are great resources worthy of reading/watching
No doubt that you can opt not to use some of the system functionality. But the question is why not utilize the full system power? It is like you by an offroad fully equipped car and just driving in the city. What is the point of buying it? What is the point of buying Construction Edition, paying a decent amount for it, and not using it and instead doing lots of manual work to keep track of your previous progress and draft your current progress? If you do not enter the budget, don't track your actuals vs budget, don’t use progress billing just right go ahead and cancel the construction edition subscription. The progress billing will help you to collaborate effectively and properly between the finance and PM team. It helps you to have a proper bill prepared and send to your clients without hassle according to your contract with the client.
Thanks for your feedback. This is a larger discussion of why it worked for us that we can have outside of a comment thread. We did optimize Acumatica for our business needs and were happy with how we used the product.
if you try to do it directly from the project with no revenue budget, you will get this message:
however, if you do it from AR and we tag this project with the “revenue” task i created, we will see the actual income amount increase. the system will also create a new line on the revenue budget for the amount that was invoiced and it will also show up on the balances tab:
the same concept can be applied to the AP side of things, you’ll just want to make sure the task is a cost task (or Cost and Revenue). but the lines will be added to the project and you can make changes to the original budgeted amount at any time as long as the budgets are locked!
Hope this helps and if you have any more construction related questions, we are happy to help!
Of course, each company can decide what for or how to use the system. What I am outlining is the best practice for construction not a MUST.
I agree, my understanding from