I have a situation where I need to have add a second AP bill to a Landed Cost Entry.

 

After I create first AP bill, the landed cost is no longer available to be used.  I tried a partial amount.  I cannot change the qty.?

Hi @phillipmarotta,

During my investigation and local testing I found out, that according to the current functionality, the system doesn’t allow to partially bill a landed cost document, so that, if 1 AP Bill is linked to a landed cost document, the system won’t allow to add the same landed cost document to another AP Bill, even if the 1st AP Bill doesn’t contain the full landed cost amount.

The requested functionality is a great suggestion. So please submit the change on the Ideas page, so that rest of the Acumatica community can see and vote for it. Additionally, the Product Management Team regular reviews items from there and comments if necessary.

As an option for your scenario, you may create a separate landed cost document for entering another AP Bill document.